Carmichael Mine Coal Handling Plant

LOCATION
QLD

CLIENT
G&S Engineering

VALUE
$30M

COMPLETION DATE
December 2021

VOLUME
4,000m3 Concrete

As part of the Carmichael Coal Mine CHPP (Coal Handling Processing Plant) located in Queensland, inland from Mackay, Whittens is performed civil installation works involving 4,000m3 of in-situ concrete works.

The scope of work for the Seperable Portion 1 works included:

  • RFP concrete work for several structures in the Carmichael Coal Mine
  • Related detailed earthworks including trenching
  • Supply and installation of pipework and cables
  • Installation of earthing system.

Following the award of the first package, Whittens were subsequently awarded Separable Portion 3 of the project, which included installation of an additional 5,000m3 insitu concrete, 200,000m3 of earthworks, and buried services construction.

 